NEW QUESTION 1
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

  • A. Control Schedule
  • B. Define Activities
  • C. Develop Schedule
  • D. Estimate Activity Resources

Answer: D

NEW QUESTION 2
Plan-do-check-act is also known as:

  • A. prevention over inspection.
  • B. statistical sampling.
  • C. management responsibility,
  • D. continuous improvemen

Answer: D

NEW QUESTION 3
Conflict should be best addressed in which manner?

  • A. Early, in private, using a direct, collaborative approach
  • B. Early, in public, using an indirect, collaborative approach
  • C. Early, in private, using an indirect, cooperative approach
  • D. As late as possible, in public, using a direct, confrontational approach

Answer: A

NEW QUESTION 4
Reserve analysis is a tool and technique used in which process?

  • A. Plan Risk Management
  • B. Plan Risk Responses
  • C. Identify Risks
  • D. Control Risks

Answer: D

NEW QUESTION 5
Which tool and technique is used in Conduct Procurements?

  • A. Teaming agreements
  • B. Expert judgment
  • C. Bidder conferences
  • D. Contract types

Answer: C

NEW QUESTION 6
Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and product

Answer: A

NEW QUESTION 7
Which of the following is a tool and technique used in the Develop Schedule process?

  • A. Three-point estimates
  • B. Resource leveling
  • C. Precedence diagramming method
  • D. Bottom-up estimating

Answer: B

NEW QUESTION 8
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

  • A. Expert judgment
  • B. Forecasting methods
  • C. Earned value management
  • D. Analytical techniques

Answer: D

NEW QUESTION 9
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

  • A. updates.
  • B. defect repairs.
  • C. preventive actions.
  • D. corrective action

Answer: A

NEW QUESTION 10
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

  • A. Estimate at completion
  • B. Cost performance
  • C. Schedule performance
  • D. To-complete performance

Answer: D

NEW QUESTION 11
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

  • A. majority rule technique.
  • B. nominal group technique.
  • C. Delphi technique,
  • D. idea/mind mapping techniqu

Answer: B

NEW QUESTION 12
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

  • A. Procurement documents
  • B. Communications plan
  • C. Project charter
  • D. Stakeholder register

Answer: C

NEW QUESTION 13
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  • A. Negative
  • B. Zero
  • C. Positive
  • D. Free

Answer: C

NEW QUESTION 14
An input to Close Project or Phase is:

  • A. Accepted deliverables,
  • B. Final products or services,
  • C. Document updates,
  • D. Work performance information.

Answer: A

NEW QUESTION 15
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  • A. Requirements documentation
  • B. Requirements traceability matrix
  • C. Project management plan updates
  • D. Project documents updates

Answer: B

NEW QUESTION 16
The Human Resource Management processes are:

  • A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
  • B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
  • C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
  • D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Tea

Answer: A

NEW QUESTION 17
In a weak matrix, the project managers role is:

  • A. part-time
  • B. full-time
  • C. occasional
  • D. unlimited

Answer: A

NEW QUESTION 18
Which process occurs within the Monitoring and Controlling Process Group?

  • A. Control Costs
  • B. Plan Quality
  • C. Perform Quantitative Risk Analysis
  • D. Determine Budget

Answer: A