NEW QUESTION 1
To which process is work performance information an input?

  • A. Administer Procurements
  • B. Direct and Manage Project Execution
  • C. Create WBS
  • D. Perform Qualitative Risk Analysis

Answer: A

NEW QUESTION 2
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

  • A. Project Plan
  • B. Responsibility Matrix
  • C. Issue Log
  • D. Scope Document

Answer: C

NEW QUESTION 3
A weighting system is a tool for which area of Conduct Procurements?

  • A. Plan contracting
  • B. Requesting seller responses
  • C. Selecting seller's
  • D. Planning purchase and acquisition

Answer: C

NEW QUESTION 4
Which of the following is an output of the Monitor and Control Project Work process?

  • A. Change requests
  • B. Performance reports
  • C. Organizational process assets
  • D. Project management plan

Answer: A

NEW QUESTION 5
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming

Answer: C

NEW QUESTION 6
How is the schedule variance calculated using the earned value technique?

  • A. EV less AC
  • B. AC less PV
  • C. EV less PV
  • D. AC less EV

Answer: C

NEW QUESTION 7
Which of the following Process Groups covers all nine Project Management Knowledge Areas?

  • A. Executing
  • B. Monitoring and Controlling
  • C. Planning
  • D. Initiating

Answer: C

NEW QUESTION 8
One of the tools and techniques of the Manage Project Team process is:

  • A. organization charts.
  • B. ground rules.
  • C. organizational theory,
  • D. conflict managemen

Answer: D

NEW QUESTION 9
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

  • A. Supportive
  • B. Directive
  • C. Controlling
  • D. Instructive

Answer: A

NEW QUESTION 10
When is a Salience Model used?

  • A. In a work breakdown structure (WBS)
  • B. During quality assurance
  • C. In stakeholder analysis
  • D. During quality control (QC)

Answer: C

NEW QUESTION 11
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

  • A. $50
  • B. $100
  • C. $125
  • D. $175

Answer: C

NEW QUESTION 12
Success is measured by benefits realization for a:

  • A. strategic plan
  • B. project
  • C. portfolio
  • D. program

Answer: C

NEW QUESTION 13
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

  • A. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
  • B. Cost-Reimbursable Contract (CR)
  • C. Firm-Fixed -Price Contract (FFP)
  • D. Fixed-Price-Incentive-Fee Contract (FPIF)

Answer: C

NEW QUESTION 14
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

  • A. project documents updates.
  • B. project management plan updates.
  • C. change requests.
  • D. work performance informatio

Answer: D

NEW QUESTION 15
Which input to the Plan Risk Management process provides information on high-level risks?

  • A. Project charter
  • B. Enterprise environmental factors
  • C. Stakeholder register
  • D. Organizational process assets

Answer: A

NEW QUESTION 16
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

  • A. Plan Risk Responses
  • B. Manage Stakeholder Expectations
  • C. Define Scope
  • D. Report Performance

Answer: B

NEW QUESTION 17
Which of the following is a tool or technique used in the Acquire Project Team process?

  • A. Networking
  • B. Training
  • C. Negotiation
  • D. Issue log

Answer: C

NEW QUESTION 18
What is the number of stakeholders, if the project has 28 potential communication channels?

  • A. 7
  • B. 8
  • C. 14
  • D. 16

Answer: B