NEW QUESTION 1
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
- A. Control Schedule
- B. Define Activities
- C. Develop Schedule
- D. Estimate Activity Resources
Answer: D
NEW QUESTION 2
Plan-do-check-act is also known as:
- A. prevention over inspection.
- B. statistical sampling.
- C. management responsibility,
- D. continuous improvemen
Answer: D
NEW QUESTION 3
Conflict should be best addressed in which manner?
- A. Early, in private, using a direct, collaborative approach
- B. Early, in public, using an indirect, collaborative approach
- C. Early, in private, using an indirect, cooperative approach
- D. As late as possible, in public, using a direct, confrontational approach
Answer: A
NEW QUESTION 4
Reserve analysis is a tool and technique used in which process?
- A. Plan Risk Management
- B. Plan Risk Responses
- C. Identify Risks
- D. Control Risks
Answer: D
NEW QUESTION 5
Which tool and technique is used in Conduct Procurements?
- A. Teaming agreements
- B. Expert judgment
- C. Bidder conferences
- D. Contract types
Answer: C
NEW QUESTION 6
Typical outcomes of a project include:
- A. Products, services, and improvements.
- B. Products, programs, and services.
- C. Improvements, portfolios, and services.
- D. Improvements, processes, and product
Answer: A
NEW QUESTION 7
Which of the following is a tool and technique used in the Develop Schedule process?
- A. Three-point estimates
- B. Resource leveling
- C. Precedence diagramming method
- D. Bottom-up estimating
Answer: B
NEW QUESTION 8
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
- A. Expert judgment
- B. Forecasting methods
- C. Earned value management
- D. Analytical techniques
Answer: D
NEW QUESTION 9
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
- A. updates.
- B. defect repairs.
- C. preventive actions.
- D. corrective action
Answer: A
NEW QUESTION 10
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
- A. Estimate at completion
- B. Cost performance
- C. Schedule performance
- D. To-complete performance
Answer: D
NEW QUESTION 11
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
- A. majority rule technique.
- B. nominal group technique.
- C. Delphi technique,
- D. idea/mind mapping techniqu
Answer: B
NEW QUESTION 12
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
- A. Procurement documents
- B. Communications plan
- C. Project charter
- D. Stakeholder register
Answer: C
NEW QUESTION 13
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
- A. Negative
- B. Zero
- C. Positive
- D. Free
Answer: C
NEW QUESTION 14
An input to Close Project or Phase is:
- A. Accepted deliverables,
- B. Final products or services,
- C. Document updates,
- D. Work performance information.
Answer: A
NEW QUESTION 15
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
- A. Requirements documentation
- B. Requirements traceability matrix
- C. Project management plan updates
- D. Project documents updates
Answer: B
NEW QUESTION 16
The Human Resource Management processes are:
- A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
- B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
- C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
- D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Tea
Answer: A
NEW QUESTION 17
In a weak matrix, the project managers role is:
- A. part-time
- B. full-time
- C. occasional
- D. unlimited
Answer: A
NEW QUESTION 18
Which process occurs within the Monitoring and Controlling Process Group?
- A. Control Costs
- B. Plan Quality
- C. Perform Quantitative Risk Analysis
- D. Determine Budget
Answer: A