NEW QUESTION 1
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost
= $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

  • A. 0.8
  • B. 0.89
  • C. 1.13
  • D. 1.25

Answer: A

NEW QUESTION 2
Sensitivity analysis is typically displayed as a/an:

  • A. Decision tree diagram.
  • B. Tornado diagram.
  • C. Pareto diagram.
  • D. Ishikawa diagram.

Answer: B

NEW QUESTION 3
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

  • A. divided among each of the phases or subprojects.
  • B. repeated for each of the phases or subprojects.
  • C. linked to specific phases or subprojects.
  • D. integrated for specific phases or subprojects.

Answer: B

NEW QUESTION 4
Which process determines the risks that may affect the project and documents their characteristics?

  • A. Control Risks
  • B. Plan Risk Management
  • C. Plan Risk Responses
  • D. Identify Risks

Answer: D

NEW QUESTION 5
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

  • A. Project
  • B. Functional
  • C. Program
  • D. Portfolio

Answer: D

NEW QUESTION 6
Which is an output from Distribute Information?

  • A. Earned value analysis
  • B. Trend analysis
  • C. Project records
  • D. Performance reviews

Answer: C

NEW QUESTION 7
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

  • A. Histogram
  • B. Quality audits
  • C. Benchmarking
  • D. Performance measurement analysis

Answer: C

NEW QUESTION 8
Scope verification is PRIMARILY concerned with which of the following?

  • A. Acceptance of the work deliverables.
  • B. Accuracy of the work deliverables.
  • C. Approval of the scope statement.
  • D. Accuracy of the work breakdown structure.

Answer: A

NEW QUESTION 9
At the start of a typical project life cycle, costs are:

  • A. low, peak as work is carried out, and drop as the project nears the end.
  • B. low, become steady as work is carried out, and increase as the project nears the end.
  • C. high, drop as work is carried out, and increase as the project nears the end.
  • D. high, become low as work is carried out, and drop as the project nears the end.

Answer: A

NEW QUESTION 10
An input to the Create WBS process is a:

  • A. project charter.
  • B. stakeholder register.
  • C. project scope statement.
  • D. requirements traceability matrix.

Answer: C

NEW QUESTION 11
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

  • A. Determine Budget.
  • B. Baseline Budget.
  • C. Control Costs.
  • D. Estimate Costs.

Answer: A

NEW QUESTION 12
Which of the following is a tool and technique for activity duration estimating?

  • A. Parametric estimating
  • B. Monte Carlo analysis
  • C. Top-down estimating
  • D. Bottom-up estimating

Answer: A

NEW QUESTION 13
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

  • A. Forecasting,
  • B. Brainstorming.
  • C. Historical databases.
  • D. Cost of quality.

Answer: D

NEW QUESTION 14
Which schedule development technique modifies the project schedule to account for limited resources?

  • A. Human resource planning
  • B. Fast tracking
  • C. Critical chain method
  • D. Rolling wave planning

Answer: C

NEW QUESTION 15
An output of the Perform Integrated Change Control process is:

  • A. Deliverables.
  • B. Validated changes.
  • C. The change log.
  • D. The requirements traceability matrix.

Answer: C

NEW QUESTION 16
Where are product requirements and characteristics documented?

  • A. Product scope description
  • B. Project charter
  • C. Preliminary project scope statement
  • D. Communications management plan

Answer: A